Describe your food and how it is made, draw the flow from delivery to dispatch, list the hazards at each step, pick the critical control points, set a limit for each, then decide how you will monitor it, what you will do when it fails, how you will check the plan works, and what you will record.
Build my free HACCP planBefore you start
A HACCP plan sits on top of the basics: clean premises, trained staff, pest control, supplier checks, cleaning schedules and temperature control. These are called prerequisite programmes. If they are weak, no plan will rescue you, so get them in place first. Then do these four things.
- Pick the team. The plan should not be one person’s homework. Include whoever knows how the food is really made, usually a chef or production lead, plus whoever buys and whoever cleans.
- Describe each product or group of similar products. Ingredients, allergens, how it is made, how it is packed, shelf life, how it is stored, who eats it (watch for vulnerable groups), and how it is meant to be used.
- Draw the flow. A simple chart from delivery to dispatch or service. One box per step: goods in, storage, preparation, cooking, cooling, holding, packing, delivery.
- Walk the flow on site. Check the chart against what really happens, on a real shift. This is where plans are most often wrong.
The seven HACCP principles
- 1
Hazard analysis
At each step, list what could cause harm. Use four groups: biological (bacteria, viruses, parasites), chemical (cleaning products, pesticides, mycotoxins), physical (glass, metal, plastic, bone) and allergens. For each hazard, note how likely it is and how serious, and what you already do to control it.
- 2
Identify the critical control points
A critical control point, or CCP, is a step where you can prevent, remove or reduce a hazard to a safe level and where nothing later in the process will do the job. Cooking chicken to a safe core temperature is a CCP for many businesses. Cleaning a surface usually is not, because a prerequisite programme controls it.
Most businesses end up with only a handful of CCPs. If you have thirty, you are probably calling everything a CCP.
- 3
Set critical limits
A critical limit is the measurable line between safe and unsafe at a CCP. It has to be something you can check on the spot. The common UK limits are below.
The three limits to remember
- Cook to 70°C for 2 minutes at the core, or an equivalent such as 75°C for 30 seconds.
- Hold hot at 63°C or above.
- Keep cold at 8°C or below. Aim for 5°C, which is the FSA target and the working limit in Scotland.
Source: GOV.UK, cooking food safely, and chilling and freezing.
| Control | Limit | Source |
|---|---|---|
| Cooking | 70°C for 2 minutes at the core, or an equivalent such as 75°C for 30 seconds or 80°C for 6 seconds | GOV.UK, cooking food safely |
| Hot holding | 63°C or above. Below 63°C for up to 2 hours is allowed once, then cool or discard | GOV.UK, cooking food safely |
| Chilled storage | 8°C or below (legal maximum in England, Wales and Northern Ireland). The FSA target is 5°C, and in Scotland the working limit is 5°C | GOV.UK, chilling and freezing |
If no standard figure exists for your process, for example a particular cooling time, you set the limit yourself and prove it works by testing. That is called validation.
- 4
Monitor
Decide who checks each CCP, with what (a calibrated probe, a timer, a pH meter), and how often. Daily or per batch is typical. Write it down so a new member of staff can do it without asking.
- 5
Corrective actions
For each CCP, decide in advance what happens when a limit is missed. For example: keep cooking until it reaches the limit, or throw it away if it has been in the danger zone too long. Say who decides, and what happens to the affected food.
- 6
Verification
Verification checks that the system works. Calibrate probes, review records, test samples where relevant, audit the plan, and re-read it whenever you change a recipe, supplier, equipment or process. A plan that was right two years ago may not be right today.
- 7
Records
Keep the plan itself, the monitoring records, the corrective actions, calibration, training and verification. The law expects records proportionate to the size and nature of the business. An environmental health officer, or a customer or certification auditor, will ask to see them.
Small caterers and shops do not always need a long document. The Food Standards Agency’s Safer Food, Better Business packs are an accepted way for many small businesses to meet the legal duty. Larger producers, and anyone supplying a retailer or certified to a scheme such as BRCGS, will normally need a fuller documented HACCP system.
Build your plan in about 10 minutes
Describe your business in your own words. The free generator drafts the hazards, critical control points, limits with their source, monitoring and records for you to edit and download.
Build my free HACCP planQuestions
How long does it take to write a HACCP plan?
A small food business can draft a plan in a day or two once the prerequisite programmes are in place. Validating it and training staff takes longer. A generator can produce a first draft in about 10 minutes, but a competent person still needs to check it against how your business really works.
Who can write a HACCP plan?
Anyone competent in your business and in food safety principles. There is no licence for writing one in the UK. Many businesses write their own, ideally with a trained HACCP team, and bring in a consultant for complex or high-risk products.
What temperatures should be in a UK HACCP plan?
Common limits are 70°C for 2 minutes at the core for cooking, 63°C or above for hot holding, and 8°C or below for chilled food, with 5°C the FSA target and the working limit in Scotland. Check the current GOV.UK and FSA pages for your nation, and set your own validated limits for steps such as cooling.
How often should I review my HACCP plan?
Review it whenever something changes, such as a recipe, supplier, piece of equipment or process, and at least once a year even if nothing has. Record the review.
Does Scotland or Northern Ireland have different rules?